The "SAP Certified Application Associate - SAP S/4HANA Production Planning and Manufacturing" certification exam validates that the candidate possesses the fundamental and core knowledge required of the SAP S/4HANA Manufacturing consultant profile. This certification proves that the candidate has an overall understanding and inādepth technical skills to participate as a member of a project team in a mentored role.
NEW QUESTION 50
How does the new Inventory Management Data model contribute to the reduction of the data footprint?
There are 3 correct answers to this question.
Response:
- A. By eliminating fields for different stock types
- B. By eliminating inventory tables
- C. By eliminating material master tables
- D. By eliminating inventory history tables
- E. By eliminating hybrid tables
Answer: A,B,D
NEW QUESTION 51
How can you enhance the system statuses of a production order scenario with user statuses?
Please choose the correct answer.
Response:
- A. By activating the user statuses in status and action management
- B. By enhancing the system status customizing table with user statuses
- C. By creating a user profile and assigning it to the production scheduling profile
- D. By defining a status profile and assigning it to the order type
Answer: B
NEW QUESTION 52
Which master data object governs the relationship between supply source and demand source in the Kanban process?
- A. Replenishment strategy
- B. Control cycle
- C. Production supply area
- D. Rate routing
Answer: B
NEW QUESTION 53
Which document is skipped when SAP EWM is embedded in SAP S/4HANA?
Please choose the correct answer.
Response:
- A. Warehouse order
- B. Outbound delivery request
- C. Outbound delivery order
- D. Warehouse task
Answer: B
NEW QUESTION 54
In which material master views can you select the batch management checkbox?
There are 2 correct answers to this question.
Response:
- A. Work Scheduling
- B. Basic Data 1
- C. MRP 4
- D. Purchasing
Answer: A,D
NEW QUESTION 55
Your customer wants to include restricted-use stock as a potential receipt in the existing ATP check for component availability.
Which information is required to implement this change request in the scope of check?
There are 2 correct answers to this question.
Response:
- A. The checking rule from the business application
- B. The checking control for the order type
- C. The ATP category for restricted-use stock
- D. The checking group from the material master
Answer: A,D
NEW QUESTION 56
You want to triggering-house production of a semi-finished mater al before a sales order for the corresponding finished good is received. Which planning strategy supports the consumption of planned independent requirements for the semi-finished material?
- A. Make-to-order production (20)
- B. Planning without final assembly (50)
- C. Planning with final assembly (40)
- D. Planning at assembly level (70)
Answer: B
NEW QUESTION 57
In which customizing activity do you set up automatic routing selection for production orders?
Please choose the correct answer.
Response:
- A. Define order-type-dependent parameter
- B. Define production scheduling profile
- C. Define selection profiles
- D. Define scheduling parameters for production orders
Answer: A
NEW QUESTION 58
In a production process, you need a certain amount of liquid as input material. The source tank is directly connected to the reactor. How can you process consumption postings?
- A. Kanban
- B. Picking list
- C. Transfer Order
- D. Backflushing
Answer: B
NEW QUESTION 59
What are some of the advantages of using Kanban?
There are 2 correct answers to this question.
Response:
- A. It is mostly accomplished by manual postings
- B. Replenishments are based on centralized planning
- C. Replenishments are created close to the actual need
- D. It is a simplified form of production control
Answer: C,D
NEW QUESTION 60
What are some uses for the low-level code assigned to each material? Note: There are 2 correct answers to this question.
- A. It is used by product costing to determine how costs are rolled up.
- B. It is used in MRP to determine the sequence in which materials are planned.
- C. It is used by engineering to identify sub items in an engineering bill of material(BOM).
- D. It is used by ATP to determine the priority of alternative components.
Answer: A,B
NEW QUESTION 61
Which options are available for an SAP S/4HANA deployment?
There are 2 correct answers to this question.
Response:
- A. SAP S/4HANA on premise
- B. SAP S/4AHANA Enterprise Management cloud
- C. SAP S/4HANA private cloud
- D. SAP S/4HANA Professional services cloud
Answer: A,C
NEW QUESTION 62
You are working with planning strategy 40 (Planning-with-final assembly). When does consumption of planned independent requirements take place?
- A. When you create a sales order
- B. When you deliver a sales order
- C. When the MRP results are saved
- D. When you create a planned order
Answer: A
NEW QUESTION 63
You use planning strategy Finite Scheduling - with Reverse and want to allow scheduling in the past. How can you achieve this?
- A. Specify a positive offset time in the strategy profile.
- B. Specify a negative offset time in the strategy profile.
- C. Specify a positive planning horizon in the strategy profile.
- D. Specify a negative planning horizon in the strategy profile.
Answer: B
NEW QUESTION 64
A warehouse manager likes to streamline the goods receipt (GR) process for production orders. Where can you enable the automatic GR?
There are 2 correct answers to this question.
Response:
- A. Confirmation profile
- B. Production scheduling profile
- C. Scheduling margin key
- D. Operation control key
Answer: B,D
NEW QUESTION 65
......