NEW QUESTION 23
A defect in a SUT has been resolved and validated by an automated defect re-test in the current release of the software. This retest has now been added to the automated regression test suite.
Which statement BEST describes a reason why this defect could re-occur in future releases?
- A. Automated defect confirmation testing is not effective at confirming that the resolved defect will continue to work in future releases
- B. The automated regression test suite has a narrower scope of functionality
- C. The automated regression test suite is not run consistently for future releases.
- D. Theconfiguration management process does not properly control the synchronization between software archives
Answer: D
NEW QUESTION 24
A web application was released into production one year ago, it has regular release which follow a V-model lifecycle and testing is well-established and fully integration into the development lifecycle. You have beenasked to implement a TAS for the regression test suite. The regression tests have been developed via the GUI and are expected to be run at least four times a month, for each planned release, for the whole operation solution life of the system (six years). Each screen of the GUI uses several third-party controls which are not compatible with the existing automation solutions. The environment for the automation will be stable, fully controllable and separated from other environments (development, staging, production).
What could be the MOST problematic for this TAS?
- A. Complexity to automate
- B. Sustainability of the automated environment
- C. Maturity of the test process
- D. Frequency ofuse
Answer: B
NEW QUESTION 25
Which of the following metrics could suggest, under certain condition that an automated regression test suite has NOT been updated for new functionalities added to the SUT?
- A. The ratio of commands to executable statements in the automation code of the regression test suite
- B. The defect density in the automation code of the regression test suite.
- C. The ratio of comments to executable statements in the SUT code.
- D. The SUT code coverage provided by the execution of the regression test suite.
Answer: B
NEW QUESTION 26
Which of the following BEST describes why it is important to separate test definition from test execution in a TAA?
- A. It allow choosing different paradigms (e.g event-driven) for the interaction TAS and SUT
- B. It allows specify test cases without being closely tied to the tool to run them against the SUT
- C. It allows testers to findmore defects on the SUT
- D. It allows developing steps of the test process without being closely tied to the SUT interface.
Answer: B
NEW QUESTION 27
Consider a TAS associated to dynamically changing software frequent releases. Your goal is todetermine the amount of effort required to maintain the automated tests of the regression test suite for each new release of the SUT.
What is the MOST important metric to collect to achieve your goal?
- A. The number ofautomated tests requiring maintenance, for each new release of the SUT.
- B. The code coverage achieved with the automated tests,for each new release of the SUT
- C. The time it takes to execute all the automated tests, for each new release of the SUT.
- D. The number of automated tests which fail because of a single software defect, for each new release of the SUT
Answer: D
NEW QUESTION 28
A defect in a SUT has been resolved and validated by an automated defect re-test in the current release of the software. This retest has now been addedto the automated regression test suite.
Which statement BEST describes a reason why this defect could re-occur in future releases?
- A. Automated defect confirmation testing is not effective at confirming that the resolved defect will continue to work in future releases
- B. The automated regression test suite has a narrower scope of functionality
- C. The configuration management process does not properly control the synchronization between software archives
- D. The automated regression test suite is not run consistently for future releases.
Answer: D
NEW QUESTION 29
You have been asked todeterminea TAS for a new release of a SUT, test should be automatedwherever. The new release will consist of 5 new interfaces and an amendment to 3 existing interfaces. The new and amended interface will be deliver incrementally in 3 sprints, each lasting 2 weeks.
What would be the BEST Test Automation Solution (TAS) design in this scenario?
- A. Automate tests at both Component and System Level. Only do this automation once every interface has been fully developed or amended and manual testing has completed successfully.
- B. Automate the tests at two levels, Component and System level. Create customized hooks at Component level for interface not yet developed or amended. Only use the newly developed or amended interfaces to test at System level.
- C. Automate tests at one level only, System level. Use only the newly developed interfaces and do not create any customized interfaces/test hooks.
- D. Automate a test at once level, component level, Create customized interface/test hooks for this level where the interface has not yet been developed or amended.
Answer: A,B
NEW QUESTION 30
A SUT has an existing automated test suite.
Which of the following statements relating to the introduction of new features in the SUT is TRUE?
- A. It is generally more difficult to automate test cases for a new feature as the development has not yet started
- B. The introduction of a new feature could require updates or additions to the testware components
- C. The test automation engineer should work with the business analysts to ensure the new feature is testable
- D. Automated tests are not affected by the introduction of a new feature and running them against the new SUT is a waste of effort
Answer: D
NEW QUESTION 31
Which of thefollowingstatementsdoes NOT describe good practice for maintaining the TAS?
- A. The TAS must run in the development environment because development and programming knowledge are required for its maintainability
- B. The TAS must consist ofcomponents that can be easily replaced without affecting the overallbehavior of the TAS itself
- C. The TAS must separate the test scripts from the environment in which it runs and from the associated harnesses and artefacts
- D. The TAS must be under configuration management, along with the test suite,the testware artefacts and the test environment in which it runs
Answer: A
NEW QUESTION 32
A SUT has an existing automated test suite.
Which of the following statements relating to the introduction of new features in the SUT is TRUE?
- A. The introduction of a new feature could require updates or additions to the testware components
- B. It is generally more difficult to automate test cases for a new feature as the development has not yet started
- C. Automated tests are not affected by the introduction of a new feature and running them against the new SUT is a waste of effort
- D. The test automation engineer should work with the business analysts to ensure the new feature is testable
Answer: A
NEW QUESTION 33
You are working on a TAS for standalone application. The automated tests are developed based on a automation framework that allows interaction with GUI elements using on object orientated API. The GUI elements include menus, buttons, radio buttons, text toolbars and their properties.
Whilst automating a test, you have discovered that the GUI elements of some third party components are not identifiable by the automated tool you are using.
Which of the following is the FIRST stepthat you take to investigate this issue?
- A. Verify whether the GUI identification depends on the browser.
- B. Verify whether naming standards for variables and have been defined for the current automation solution
- C. Verify the testability support with the providers of the third party components
- D. Adopt an approach that uses the coordinates of the GUI elementsinstead
Answer: C
NEW QUESTION 34
Designing the System Under Test (SUT) for testability is important for a good test automation approach and can also benefit manual test execution.
Which of the following is NOT a consideration when designing for testability?
- A. Control: the SUT needs to provide interfaces that can be used to perform actions on SUT.
- B. Observability: The SUT needs to provide interface that give insight into the system.
- C. Re-useability: The code written for the SUT must be re-useable for other similar system.
- D. Clearly defined architecture: The SUT Architecture needs to provide clear and understandable interfaces giving control and visibility on all test levels.
Answer: C
NEW QUESTION 35
What is NOT a factor in considering when you are asked to ensure an effective transition from manual to automated tests?
- A. Correctness of test data and test cases
- B. The look andfeel of the SUT
- C. Complexity to automate the manual test cases
- D. The controllability of the SUT
Answer: B
NEW QUESTION 36
Consider the following example of TAS metrics.
Time to execute automated tests
Speed and efficiency of TAS components
Which of the following statements is TRUE?
- A. A is an internal TAS metric and B is an external TAS metric
- B. A is and external TAS metric and b is an internal TAS metric
- C. A and b are both external TAS metric
- D. A and B are both internal TAS metrics
Answer: D
NEW QUESTION 37
Which of the following statements about the reuse of TAS artefacts is TRUE?
- A. Reusable TAS artefacts can include components (or parts of components) associated with different layers of the TAA
- B. Reusable TAS artifacts associated with the definition layer of the TAA include the adaptors to the SUT components and/or interfaces
- C. To enable reuse of TAS artefacts, a good design for reuse is built into the TAA and to further action are needed during the TAS lifecycle
- D. Communications maintenance and improvements for reusing TAS artefacts are modifyaddressed during the design of the TAA
Answer: C
NEW QUESTION 38
Consider a TAS associated to dynamically changing software frequent releases. Your goal is to determine the amount of effort required to maintain the automated tests of the regression test suite for each new release of the SUT.
What is the MOST important metric to collect to achieve your goal?
- A. The code coverage achieved with the automated tests, for each new release of the SUT
- B. The time it takes to execute all the automated tests, for each new release of the SUT.
- C. The number of automated tests requiring maintenance, for each new release of the SUT.
- D. The number of automated tests which fail because of a single software defect, for each new release of the SUT
Answer: D
NEW QUESTION 39
Your goal is to verify completeness, consistency and correct behavior of an automated test suite. The TAS has been proven to successfully install in the SUTenvironment. All the preliminary checks to verify the correct functioning of the automated test environment and test tool configuration, installation and setup have successfully completed.
Which of the following is NOT a relevant check for achieving your goal in this scenario?
- A. Checking whether the loading of the TAS is repeatable in the SUT environment
- B. Checking whether the post condition have been fulfilled for all the test cases
- C. Checking whether all the test cases produce repeatable outcomes
- D. Checking whether all the test cases contain the expected results
Answer: C
NEW QUESTION 40
Which of the following success factors for a test automation project is TRUE?
- A. Automated tests that fail due to changes in the requirements of the SUT should be promptly fixed rather than disabled from the test suite
- B. Automated tests must be designed to capture only the data that is strictly needed for comparing expected and actual results
- C. The test cases to be automated first must always be selected based on the number of times a test will need to be run
- D. The test cases to be automated must have a high dependency on particular data values
Answer: A
NEW QUESTION 41
You have been asked to automate a set of functional tests at system Test level via the CLI of the SUT for the first release of a software system. The automated tests will be delivered to the learn in change of maintenance testing, who will use them for part of the regression testing. They have the following requirements.
1.The automated tests must be as fast and cheap to maintain as possible
2.The cost of adding new automated tests must be as low as possible
3.The automated tests must have a high level of independence from the tool itself Which of the following scripting techniques would be MOST suitable?
- A. Structure scripting
- B. Keyword-driven scripting
- C. Linear scripting
- D. Data-driven scripting
Answer: A
NEW QUESTION 42
......