The "SAP Certified Application Associate - SAP S/4HANA Project Systems" certification exam verifies that the candidate has the fundamental and core knowledge in the area of sourcing and procurement required for the consultant profile. This certificate proves that the candidate has an overall understanding and can implement the knowledge practically in projects to contribute to the success of the planning and implementation phases in a mentored role. Previous project experience is not necessarily a prerequisite to pass this exam.
NEW QUESTION 29
What are some of the advantages of using project simulations? Note: There are 3 correct Answers to this question.
- A. Project simulations can create purchase requisitions.
- B. Multiple project simulations can be used simultaneously.
- C. Project simulations can be used to plan structures and costs.
- D. Project simulations allow posting of actual data.
- E. Project simulations can be created without using an operational project as a template.
Answer: B,C,E
NEW QUESTION 30
You want to establish costing for WBS. Costing should be easy to use and should not refer to cost elements. What method for costing do you use?
- A. Unit costing for WBS
- B. Planning of overall values
- C. Detailed planning for WBS
- D. Easy Cost Planning (ECP) for WBS
Answer: B
NEW QUESTION 31
Which object is used to allocate the costs from a claim to the project structure?
- A. Network activity
- B. Internal order
- C. Claim
- D. WBS element
Answer: B
NEW QUESTION 32
In your logistics project, you want to carry out the internal project work as soon as possible. What do you have to maintain in capacity requirements planning?
- A. Control key of an activity
- B. Capacity planner group in the network header
- C. Scheduling and distribution key
- D. Scheduling and capacity category
Answer: A
NEW QUESTION 33
Which organizational structures are required for network activities? Note: There are 3 correct Answers to this question.
- A. Plant
- B. Sales organization
- C. Controlling area
- D. Operating concern
- E. Company code
Answer: A,C,E
NEW QUESTION 34
What business transactions can be used with Project-Oriented Procurement (ProMan)? Note: There are
3 correct Answers to this question.
- A. Generate delivery
- B. Generate purchase requisition
- C. Stock transfer posting
- D. Confirm production order
- E. Cancel goods issue
Answer: A,B,C
NEW QUESTION 35
You plan an activity that starts on February 1 and finishes on February 28. For this activity, you want to define a milestone for February 10 which should NOT be changed through scheduling. What do you recommend for milestone definition?
- A. Enter an offset of 10 days to the start date of the activity.
- B. Enter an offset of -18 days to the finish date of the activity.
- C. Enter 10 days as duration.
- D. Enter February 10 as fixed date.
Answer: D
NEW QUESTION 36
Which of the following business processes do NOT lead to the booking of actual costs to an object?
Note: There are 2 correct Answers to this question.
- A. Goods receipt of a non-stock item
- B. Goods receipt into valuated project stock
- C. Recording of external services in the service entry sheet
- D. Goods receipt into unvaluated project stock
Answer: C,D
NEW QUESTION 37
Your customer wants to use requirements grouping in SAP Project System. What are the prerequisites for requirements grouping of materials? Note: There are 2 correct Answers to this question.
- A. An MRP group must be assigned.
- B. The exact lot size procedure must be used.
- C. The procurement type of the material must be internal.
- D. The materials must allow sales order or project stock.
Answer: A,D
NEW QUESTION 38
You want to create a reservation for a material component assigned to a network activity. However, after releasing and saving the activity, no reservation is created. What are some possible reasons for the missing reservation? Note: There are 2 correct Answers to this question.
- A. The material master is set to external procurement.
- B. The material is assigned to the activity as a non-stock material.
- C. The indicator Reservation/Purchase Requisition indicator for the material component assigned to the activity is set to "never".
- D. The availability check for material components indicates missing parts.
Answer: C,D
NEW QUESTION 39
Where can you define a network as "header-account-assigned" or "activity-account-assigned"?
- A. Parameters for the network type
- B. Network profile
- C. Network type
- D. Project profile
Answer: A
NEW QUESTION 40
Which statement is valid regarding networks? Note: There are 2 correct Answers to this question.
- A. Material components can be assigned to activity elements.
- B. A network can be activity-account-assigned and header-account-assigned.
- C. A network activity can be assigned to several WBS elements.
- D. Relationships can be used to connect activities of different networks.
Answer: B,D
NEW QUESTION 41
How are earliest dates and latest dates of activities scheduled?
- A. Earliest dates are scheduled by forward scheduling, and latest dates by backward scheduling.
- B. Earliest dates are scheduled by backward scheduling, and latest dates by forward scheduling.
- C. Earliest dates are scheduled by backward scheduling, and latest dates by copying the earliest dates.
- D. Earliest dates and latest dates are scheduled by forward scheduling.
Answer: A
NEW QUESTION 42
What are some of the possible functions in user status profiles? Note: There are 2 correct Answers to this question.
- A. Utilize priorities for setting the user status.
- B. Ensure user status must always be set manually.
- C. Allow business processes forbidden by SAP system status.
- D. Restrict setting user status for individual users.
Answer: A,D
NEW QUESTION 43
You have assigned a budget to WBS elements within your project. What function can be used to check assigned values against the current budget?
- A. Results analysis
- B. Cost forecast
- C. Availability control
- D. Easy Cost Planning
Answer: C
NEW QUESTION 44
How can you grant individual authorization for WBS elements and networks?
- A. Activate access control lists (ACL) for the project profile and the network profile.
- B. Set the system status to "Lock Master Data".
- C. Define a user status to lock the business transaction Update Project.
- D. Activate access control lists (ACL) for the user master record.
Answer: A
NEW QUESTION 45
Where do you maintain the length of the project ID?
- A. Project coding mask
- B. Project profile
- C. Project type
- D. Special characters
Answer: A
NEW QUESTION 46
What are valid procurement types for stock items? Note: There are 3 correct Answers to this question.
- A. Third-party order
- B. Purchase requisition and Reservation for WBS element
- C. Preliminary purchase requisition for WBS element
- D. Planned order
- E. Reservation for WBS element
Answer: B,C,E